LatestCountriesDevelopersSearch

Countries β€Ί Thailand

πŸ‡ΉπŸ‡­ Carbon projects in Thailand

138 listed todayData as of 2026-11-23

Read the Thailand market guide β†’ Policy, buyers and what to watch. This page is the full project list behind it.

Covered by the Southeast Asia edition of the Carbon.Supply briefing.

Expected supply: biochar, dynamic-baseline nature and JCM

Carbon.Supply screening estimate, not a registry figure and not a forecast of prices. What these projects claim, discounted by how far each has got and by how much similar projects have delivered before. How we estimate it.

149k claimed for 203027k expected in 2030range 12k to 61k

0 41k 83k 124k 166k 2026: 334 expected 2026: 821 expected 2027: 334 expected 2027: 10,476 expected 2028: 334 expected 2028: 14,107 expected 2029: 334 expected 2029: 11,659 expected 2029: 15,382 expected 2030: 334 expected 2030: 11,659 expected 2030: 14,889 expected 2031: 334 expected 2031: 11,659 expected 2031: 12,438 expected 2032: 334 expected 2032: 11,659 expected 2032: 12,160 expected 2033: 334 expected 2033: 11,659 expected 2033: 5,240 expected 2034: 334 expected 2034: 11,659 expected 2034: 5,053 expected 2035: 334 expected 2035: 11,659 expected 2035: 2,567 expected 2036: 334 expected 2036: 11,659 expected 2036: 2,458 expected 2037: 11,659 expected 2037: 1,897 expected 2038: 11,659 expected 2038: 1,897 expected 2039: 11,659 expected 2039: 1,262 expected 2040: 11,659 expected 2040: 47 expected 2041: 11,659 expected 2041: 47 expected 2042: 11,659 expected 2043: 11,659 expected 2044: 11,659 expected 2045: 11,659 expected 2046: 11,659 expected 2047: 11,659 expected 2048: 11,659 expected 2049: 11,659 expected 2050: 11,659 expected 2030 2035 2040 2045 2050
Biochar   Dynamic-baseline nature   JCM   claimed (dotted) Β· tCO2e a year, central case
GroupProjectsClaimed 2030Expected 2030Range 2030Claimed 2026–2050Expected 2026–2050
Biochar1334334234–3343,6743,674
Dynamic-baseline nature158,29611,6595,101–27,9821,457,400256,498
JCM3189,95614,8896,852–33,049753,106100,741
All other types962,844,161884,074467,389–1,569,75325,368,7217,233,097

Focus projects

ProjectRegistryGroupStageClaimed 2030Expected 2030t CO2e per ha a yearBasis of the claim
SCGPuro.earth 133972BiocharIssuing334334–issued run rate (668 over 2 yr), one renewal assumed, to 2036
THAMMA RAKSA - REFORESTATION AND LAND RESTORATION IN THAILANDVerra VCS 3581Dynamic-baseline naturePipeline58,29611,6594.7registry estimate 58,296 a year, 2024 to 2064
Power Generation by Waste Heat Recovery in Cement IndustryJCM (Japan) TH006JCMRegistered, not yet issuing29,7465,563–JCM yearly schedule to 2030, held at the 2030 level to 2032
Low-carbon Operation for Power Grid Utilizing Online Voltage-var(Q) Optimal Control (OPENVQ) with ICTJCM (Japan) TH024JCMIn validation17,9562,370–JCM yearly schedule to 2030
Introduction of 30MW Rooftop Solar Power System to Large SupermarketsJCM (Japan) TH009JCMRegistered, not yet issuing13,2932,486–JCM yearly schedule to 2030, held at the 2030 level to 2034
17.8MW Rooftop and Floating Solar Power Project in Industrial ParkJCM (Japan) TH027JCMIn validation7,471986–JCM yearly schedule to 2030, held at the 2030 level to 2039
Installation of Co-Generation Plant for On-Site Energy Supply and High Efficiency Non-Inverter Type Centrifugal Chiller in Motorcycle FactoryJCM (Japan) TH013JCMRegistered, not yet issuing7,2621,358–JCM yearly schedule to 2030, held at the 2030 level to 2032
Introduction of 8.1MW Rooftop Solar Power System in Motorcycle Factory and Fiber FactoryJCM (Japan) TH028JCMIn validation3,648482–JCM yearly schedule to 2030, held at the 2030 level to 2038
Introduction of 5MW Floating Solar Power System on Industrial Water Reservoir in ThailandJCM (Japan) TH014JCMIssuing2,552561–JCM yearly schedule to 2030, held at the 2030 level to 2036
Introduction of 5MW Rooftop Solar Power System to Aluminum Building Materials FactoryJCM (Japan) TH033JCMIn validation2,103278–JCM yearly schedule to 2030, held at the 2030 level to 2031
Introduction of 3.4 MW Rooftop Solar Power System in Technical Center and Office BuildingsJCM (Japan) TH015JCMIn validation1,417187–JCM yearly schedule to 2030, held at the 2030 level to 2033
Introduction of 2.6MW Rooftop Solar Power System to Semiconductor FactoryJCM (Japan) TH029JCMIn validation1,159153–JCM yearly schedule to 2030, held at the 2030 level to 2038
Introduction of 2MW Rooftop Solar Power System to Non-ferrous Metal FactoryJCM (Japan) TH030JCMIn validation905119–JCM yearly schedule to 2030, held at the 2030 level to 2039
Introduction of 2MW Rooftop Solar Power System to UniversityJCM (Japan) TH034JCMIn validation831110–JCM yearly schedule to 2030, held at the 2030 level to 2039
Introduction of 0.8MW Solar Power System and High Efficiency Refrigerator to Food FactoryJCM (Japan) TH022JCMRegistered, not yet issuing43381–JCM yearly schedule to 2030
Introduction of 0.97 MW Rooftop Solar Power System for Fishery Net FactoryJCM (Japan) TH017JCMIn validation42556–JCM yearly schedule to 2030, held at the 2030 level to 2035
Introduction of 0.95 MW Rooftop Solar Power System in Cigarette Lighter FactoryJCM (Japan) TH016JCMIn validation40053–JCM yearly schedule to 2030, held at the 2030 level to 2035
Energy Supply Project by 0.9MW Rooftop Solar Power System to Metal Recycling and Automotive Parts FactoriesJCM (Japan) TH026JCMIn validation35547–JCM yearly schedule to 2030, held at the 2030 level to 2041
Energy saving by installation of evaporator with mechanical vapor recompression and high-efficiency chiller.JCM (Japan) TH021JCMIn validation00–JCM yearly schedule to 2026
Energy Saving by Introduction of High Efficiency Chilled Water Supply System in Milk FactoryJCM (Japan) TH019JCMIn validation00–JCM yearly schedule to 2027
Energy Saving for Air conditioning in Tire Manufacturing Factory with High Efficiency Centrifugal ChillerJCM (Japan) TH007JCMRegistered, not yet issuing00–JCM yearly schedule to 2027
Energy Saving for Semiconductor Factory with High Efficiency Centrifugal Chiller and CompressorJCM (Japan) TH004JCMIssuing00–JCM yearly schedule to 2025
Installation of Energy-efficient Refrigerators Using Natural Refrigerant at Distribution Centre of Better Foods Co., Ltd.JCM (Japan) TH020JCMIn validation00–JCM yearly schedule to 2027
Installation of High Efficiency Air Conditioning System and Chillers in Semiconductor FactoryJCM (Japan) TH003JCMIssuing00–JCM yearly schedule to 2025
Introduction of 0.13MW Solar Power System to Auto Parts FactoryJCM (Japan) TH032JCMIn validation00–JCM yearly schedule to 2029
Introduction of 1.3MW Solar Power System to Food FactoriesJCM (Japan) TH031JCMIn validation00–JCM yearly schedule to 2028
Introduction of 3.4MW Rooftop Solar Power System to Air-conditioning Parts FactoriesJCM (Japan) TH005JCMIssuing00–JCM yearly schedule to 2027
Introduction of Heat Recovery Heat Pumps to a Chicken Slaughtering Plant in ThailandJCM (Japan) TH008JCMRegistered, not yet issuing00–JCM yearly schedule to 2027
Introduction of High Efficiency Ion Exchange Membrane Electrolyzer in Caustic Soda Production PlantJCM (Japan) TH023JCMIn validation00–JCM yearly schedule to 2027
Introduction of High-efficiency Boiler System to Rubber Belt PlantJCM (Japan) TH018JCMIn validation00–JCM yearly schedule to 2027
Introduction of Solar PV Systems on Rooftops of Factory and Office BuildingJCM (Japan) TH001JCMIssuing00–JCM yearly schedule to 2020, held at the 2020 level to 2025
LED lighting introduction business for the sales store.JCM (Japan) TH025JCMIn validation00–JCM yearly schedule to 2025, held at the 2025 level to 2026
Reducing GHG emission at Textile Factory of Luckytex (Thailand) Public Company Limited by Upgrading to Air-saving LoomJCM (Japan) TH002JCMIssuing00–JCM yearly schedule to 2023
How we estimate it

Claimed volume comes from the project description's own yearly table where we have read it, otherwise from the registry's annual estimate over the crediting period, from JCM's own yearly schedule, or, for biochar, from the rate the project has already issued at. Expected volume multiplies it by the chance of reaching issuance from the current stage (central case: pipeline 40%, in validation 60%, registered and not yet issuing 85%, issuing 100%, at risk 30%) and by the share of their claim that similar projects have delivered (dynamic-baseline nature 50%, JCM 22%, biochar 100%, other types 36%), from Berkeley Carbon Trading Project data and the JCM registry. Credits start one to three years from now depending on stage. Carbon per hectare is the yearly average of the project description's table on the area that document gives, or else the registry estimate divided by the area the proponent entered; either can be a first planting instance rather than the whole project. Project descriptions stay on the registry: follow the project link to read them. Screening estimate, updated daily; the method will change as we read more design documents.

Issued and retired

From Verra's own issuance and retirement records, every row since the registry began, as of 2026-11-23. Gold Standard not yet included.

13,939,989 credits issued11,215,172 retired80.5% of issued credits retired2,627 retirements

Who the credits were retired for

Beneficiary, as the registry publishes itCredits retiredRetirementsProjectsLatest
_226,91365102022-04-20
Yamato Transport Co., Ltd156,229322026-09-18
Chevron Petroleum Company S.A NIT 860.005.223-9148,0261132017-10-20
Terpel S.A125,628832017-08-15
4AIR104,7411232026-09-09
Qantas Airways Limited83,6962212021-06-24
Organizacion Terpel identificada con NIT 830.095.213-079,968722017-08-18
Schweizgas Klima75,9251152023-03-02
BRISBANE CITY COUNCIL71,700622023-09-14
The Boeing Company51,258732024-02-16
Germany50,000112019-01-21
USA50,000112019-01-21
KPMG Australia39,814112020-06-11
LifeGate Climate Action per PostePay38,000112024-11-19
On Behalf of McKinsey & Co.'s 2022 GHG Emissions38,000422022-12-05
Other named beneficiaries1,034,683
No public beneficiary8,840,591

Names are the registry's beneficial-owner field where the registry marks it public. Beneficiaries under 1,000 credits are not named here.

By vintage

VintageIssuedRetiredissued retired
20041,8711,871
20058,0128,012
2006649,298597,194
20071,116,4761,028,238
20081,136,2071,089,263
20091,022,1671,018,941
2010876,441860,623
2011665,244590,981
2012845,893747,387
2013724,550590,506
2014708,678641,408
2015606,847581,243
2016505,072488,555
2017409,062389,015
2018411,159404,534
20191,189,0331,032,211
20201,008,652626,967
2021999,246324,715
2022745,089168,892
2023268,54124,616
202442,4510

By year

YearIssued that yearRetired that year
2009307,83090,153
20101,025,584577,400
20111,837,550568,568
20121,496,795605,566
2013462,9081,406,007
201452,961406,842
201549,628742,291
2016252,186404,205
2017939,879845,789
2018843,840720,675
2019914,687880,333
20201,402,276716,226
20211,676,1261,214,008
20221,087,130769,149
2023774,707451,648
2024322,445312,999
2025197,791149,936
2026295,666353,377

By project

ProjectIssuedRetired
Siam Cement Biomass Project4,015,0043,894,097
Wastewater Treatment with Biogas Production (UASB) and Heat Utilization at General Starch Co Ltd.831,722571,925
THEPARAK WIND IN THAILAND659,274237,805
TROPICAL WIND IN THAILAND628,720493,982
K.R.S. THREE IN THAILAND624,808266,281
Chol Charoen Group Wastewater Treatment with Biogas System I (Cholburi)565,708556,794
KRISSANA WIND POWER IN THAILAND556,524205,911
P.S.C Starch Wastewater Treatment and Biogas Utilization Project552,013550,002
SD Biosupply Wastewater Treatment and Biogas Utilization Project522,618494,361
Reduction of GHG emissions in Propylene Oxide production at MTP HPPO Manufacturing Co., Ltd507,139500,000
VP Biosupply Wastewater Treatment and Biogas Utilization Project493,911452,421
Chol Charoen Group Wastewater Treatment with Biogas System I (Khonkaen)478,036430,008
K.R. ONE IN THAILAND431,188124,065
Chol Charoen Group Wastewater Treatment with Biogas System I (Chacherngsao)362,942353,899
Chorchaiwat Wastewater Treatment and Biogas Utilization Project304,079304,079
Banpong Tapioca Flour Industrial Wastewater Treatment and Biogas Utilisation Project258,762252,078
Installation of high efficiency wood burning cookstoves in Thailand217,099158
Wastewater Treatment with Biogas System in Palm Oil Mill at Sawi, Chumporn,Thailand195,54795,219
Mungcharoen Green Power - 9.9 MW Rice Husk Fired Power Plant Project158,178154,849
Siam Quality Starch Wastewater Treatment and Energy Generation Project in Chaiyaphum, Thailand156,31646,004
CYY Biopower Wastewater treatment plant including biogas reuse for thermal oil replacement and electricity generation Project, Thailand147,147133,547
CYY Global Plus Wastewater Treatment and Biogas Utilization Project119,90561,410
Bangkok Kamphaeng Saen East: Landfill Gas to Electricity Project112,500100,500
The VCF Group Biogas Projects at Nipat and Songphol Farm109,929109,929
The SPM Group Biogas Project107,825107,825
Bangkok Kamphaeng Saen West: Landfill Gas to Electricity Project87,50087,500
Cassava Waste To Energy Project, Kalasin, Thailand (CWTE project)83,65583,605
Northern Fuel Pipeline Transportation Project, Thailand81,0820
Biomass powered process heat production and use project at Kangwal78,77078,770
Sahamitr Tapioca Chonburi Wastewater Treatment and Biogas Utilization Project72,53665,722
Wastewater Treatment with Biogas Technology in a Tapioca Processing Plant at P.V.D. International Company Limited, Thailand72,26772,267
Chao Khun Agro Biogas Energy Project67,74867,748
JAROENSOMPONG CORPORATION RACHATHEWA LANDFILL GAS TO ENERGY64,47364,473
Wastewater Treatment with Biogas Technology in Tapioca Processing Plant at Roi Et Flour Company Limited, Thailand59,82559,825
Kitroongruang Biogas Energy Project35,55435,054
Ratchaburi Farms Biogas Project at SPM Farm33,85333,353
Jiratpattana Biogas Energy Project30,07230,072
Ratchaburi Farms Biogas Project at Nong Bua Farm21,74721,747
FST SMALL-SCALE SOLAR POWER PLANT IN KAMPHAENG PHET, THAILAND17,4236,000
Chakangrao Starch wastewater treatment and biogas utilization project10,5909,864
Thanawat wastewater treatment and biogas utilization project3,0002,023
Ratchaburi Farms Biogas Project at Veerachai Farm3,0000

Every project

ProjectRegistryCountryRegistry statusCarbon.Supply classificationFirst seen
Bangkok Kamphaeng Saen East: Landfill Gas to Electricity ProjectGold Standard 226ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Bangkok Kamphaeng Saen West: Landfill Gas to Electricity ProjectGold Standard 225ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Bangna Starch Wastewater Treatment and Biogas Utilization Project (300084)Gold Standard 999ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Bangna Starch Wastewater Treatment and Biogas Utilization Project (300084) (GS565 CER to VER conversion)Gold Standard 1707ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Bangna Starch Wastewater Treatment and Biogas Utilization Project (300084)_pre-CDM VERGold Standard 1190ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Biogas project, Cargill Siam BorabuGold Standard 980ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Blue Fire Bio wastewater treatment and biogas utilisation project (300147)Gold Standard 1138ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Blue Fire Bio wastewater treatment and biogas utilization project (300147)_pre-CDM VERGold Standard 1191ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Chaiyaphum Wind Farm Power ProjectGold Standard 2038ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Chantaburi Starch Wastewater Treatment and Biogas Utilization Project (300085)Gold Standard 929ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Chantaburi Starch Wastewater Treatment and Biogas Utilization Project (300085)_pre-CDM VERGold Standard 1187ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Chumporn applied biogas technology for advanced waste water managementGold Standard 1509ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Clean Energy One Biomass Power Plant Project (300548)Gold Standard 1198ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Clean Energy One Biomass Power Plant Project (300548)_pre-CDM VERGold Standard 1203ThailandLISTEDPipeline2026-09-20*
CYY Biopower Wastewater treatment plant including biogas reuse for thermal oil replacement and electricity generation Project, Thailand (300059)Gold Standard 981ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
CYY Biopower Wastewater treatment plant including biogas reuse for thermal oil replacement and electricity generation Project, Thailand (300059)_pre-CDM VERGold Standard 1189ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
CYY Singha Yasothon Wastewater Treatment and Biogas Utilization ProjectGold Standard 4906ThailandLISTEDPipeline2026-09-20*
ES Energy Biomass Power PlantGold Standard 302ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
GS23612 - VPA-1 - Energy efficiency retrofits for buildings in ThailandGold Standard 5563ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
GS23612 - VPA-1 - Renewable energy generation through solar photovoltaic in ThailandGold Standard 5562ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
GS23612- VPA-1 - Energy efficient street lighting in ThailandGold Standard 5564ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
GS23612- VPA-1 - Transition to electric vehicles in ThailandGold Standard 5565ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Installation of high efficiency wood burning cookstoves in ThailandGold Standard 4911ThailandLISTEDPipeline2026-09-20*
Lam Soon Wastewater Treatment for Energy Generation, TrangGold Standard 1137ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Low Carbon Cities and Carbon Market Development ProjectGold Standard 5561ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Methane Reduction in Irrigated Rice Production, ThailandGold Standard 2056ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Metro Group Energy WWT Project (300392)Gold Standard 1172ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Metro Group Energy WWT Project (300392)_pre-CDM VERGold Standard 1196ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Papop Biogas and Renewable Energy Project in ThailandGold Standard 690ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Pitak Palm Wastewater Treatment and Biogas Utilization Project (300335)Gold Standard 914ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Pitak Palm Wastewater Treatment and Biogas Utilization Project (300335)_pre-CDM VERGold Standard 1186ThailandLISTEDPipeline2026-09-20*
Saraff Biogas Wastewater Treatment and Biogas Utilisation project (300177)Gold Standard 938ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Saraff Biogas Wastewater Treatment and Biogas Utilisation project (300177)_pre-CDM VERGold Standard 1188ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Solar Power Company 94MW ProjectGold Standard 1319ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
SSE1 Solar PV 1 – 10 Power Plant ProjectGold Standard 1676ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
TBEC Tha Chang Biogas ProjectGold Standard 817ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
TBEC Tha Chang Biogas Project PreCDMVERGold Standard 1232ThailandGOLD_STANDARD_CERTIFIED_DESIGNRegistered2026-09-20*
Univanich Lamthap POME Biogas ProjectGold Standard 813ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Univanich Lamthap POME Biogas Project PreCDMVERGold Standard 1233ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Univanich TOPI Biogas ProjectGold Standard 821ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
UPOIC Wastewater Treatment for Energy Generation, KrabiGold Standard 1135ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
West Huaybong 2 wind farm projectGold Standard 2589ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
West Huaybong 3 wind farm projectGold Standard 2591ThailandGOLD_STANDARD_CERTIFIED_PROJECTRegistered2026-09-20*
Enable Earth, Chiang RaiIsometric prj_1KBECJX991S0EDE4ThailandCANCELLEDInactive2026-09-21*
17.8MW Rooftop and Floating Solar Power Project in Industrial ParkJCM (Japan) TH027ThailandValidationIn validation2026-10-31*
Energy saving by installation of evaporator with mechanical vapor recompression and high-efficiency chiller.JCM (Japan) TH021ThailandValidationIn validation2026-10-31*
Energy Saving by Introduction of High Efficiency Chilled Water Supply System in Milk FactoryJCM (Japan) TH019ThailandValidationIn validation2026-10-31*
Energy Saving for Air conditioning in Tire Manufacturing Factory with High Efficiency Centrifugal ChillerJCM (Japan) TH007ThailandProject registeredRegistered2026-10-31*
Energy Saving for Semiconductor Factory with High Efficiency Centrifugal Chiller and CompressorJCM (Japan) TH004ThailandProject registeredRegistered2026-10-31*
Energy Supply Project by 0.9MW Rooftop Solar Power System to Metal Recycling and Automotive Parts FactoriesJCM (Japan) TH026ThailandValidationIn validation2026-10-31*
Installation of Co-Generation Plant for On-Site Energy Supply and High Efficiency Non-Inverter Type Centrifugal Chiller in Motorcycle FactoryJCM (Japan) TH013ThailandProject registeredRegistered2026-10-31*
Installation of Energy-efficient Refrigerators Using Natural Refrigerant at Distribution Centre of Better Foods Co., Ltd.JCM (Japan) TH020ThailandValidationIn validation2026-10-31*
Installation of High Efficiency Air Conditioning System and Chillers in Semiconductor FactoryJCM (Japan) TH003ThailandProject registeredRegistered2026-10-31*
Introduction of 0.13MW Solar Power System to Auto Parts FactoryJCM (Japan) TH032ThailandValidationIn validation2026-10-31*
Introduction of 0.8MW Solar Power System and High Efficiency Refrigerator to Food FactoryJCM (Japan) TH022ThailandProject registeredRegistered2026-10-31*
Introduction of 0.95 MW Rooftop Solar Power System in Cigarette Lighter FactoryJCM (Japan) TH011ThailandRequest for Registration withdrawnInactive2026-10-31*
Introduction of 0.95 MW Rooftop Solar Power System in Cigarette Lighter FactoryJCM (Japan) TH016ThailandValidationIn validation2026-10-31*
Introduction of 0.97 MW Rooftop Solar Power System for Fishery Net FactoryJCM (Japan) TH012ThailandRequest for Registration withdrawnInactive2026-10-31*
Introduction of 0.97 MW Rooftop Solar Power System for Fishery Net FactoryJCM (Japan) TH017ThailandValidationIn validation2026-10-31*
Introduction of 1.3MW Solar Power System to Food FactoriesJCM (Japan) TH031ThailandValidationIn validation2026-10-31*
Introduction of 2.6MW Rooftop Solar Power System to Semiconductor FactoryJCM (Japan) TH029ThailandValidationIn validation2026-10-31*
Introduction of 2MW Rooftop Solar Power System to Non-ferrous Metal FactoryJCM (Japan) TH030ThailandValidationIn validation2026-10-31*
Introduction of 2MW Rooftop Solar Power System to UniversityJCM (Japan) TH034ThailandValidationIn validation2026-10-31*
Introduction of 3.4 MW Rooftop Solar Power System in Technical Center and Office BuildingsJCM (Japan) TH010ThailandRequest for Registration withdrawnInactive2026-10-31*
Introduction of 3.4 MW Rooftop Solar Power System in Technical Center and Office BuildingsJCM (Japan) TH015ThailandValidationIn validation2026-10-31*
Introduction of 3.4MW Rooftop Solar Power System to Air-conditioning Parts FactoriesJCM (Japan) TH005ThailandProject registeredRegistered2026-10-31*
Introduction of 30MW Rooftop Solar Power System to Large SupermarketsJCM (Japan) TH009ThailandProject registeredRegistered2026-10-31*
Introduction of 5MW Floating Solar Power System on Industrial Water Reservoir in ThailandJCM (Japan) TH014ThailandProject registeredRegistered2026-10-31*
Introduction of 5MW Rooftop Solar Power System to Aluminum Building Materials FactoryJCM (Japan) TH033ThailandValidationIn validation2026-10-31*
Introduction of 8.1MW Rooftop Solar Power System in Motorcycle Factory and Fiber FactoryJCM (Japan) TH028ThailandValidationIn validation2026-10-31*
Introduction of Heat Recovery Heat Pumps to a Chicken Slaughtering Plant in ThailandJCM (Japan) TH008ThailandProject registeredRegistered2026-10-31*
Introduction of High Efficiency Ion Exchange Membrane Electrolyzer in Caustic Soda Production PlantJCM (Japan) TH023ThailandValidationIn validation2026-10-31*
Introduction of High-efficiency Boiler System to Rubber Belt PlantJCM (Japan) TH018ThailandValidationIn validation2026-10-31*
Introduction of Solar PV Systems on Rooftops of Factory and Office BuildingJCM (Japan) TH001ThailandProject registeredRegistered2026-10-31*
LED lighting introduction business for the sales store.JCM (Japan) TH025ThailandValidationIn validation2026-10-31*
Low-carbon Operation for Power Grid Utilizing Online Voltage-var(Q) Optimal Control (OPENVQ) with ICTJCM (Japan) TH024ThailandValidationIn validation2026-10-31*
Power Generation by Waste Heat Recovery in Cement IndustryJCM (Japan) TH006ThailandProject registeredRegistered2026-10-31*
Reducing GHG emission at Textile Factory of Luckytex (Thailand) Public Company Limited by Upgrading to Air-saving LoomJCM (Japan) TH002ThailandProject registeredRegistered2026-10-31*
SCGPuro.earth 133972ThailandlistedRegistered2026-10-31*
8 MW NongKhai Waste to Energy Project in ThailandVerra VCS 4012ThailandUnder validation (Public comment period closed)In validation2026-09-20*
Bangkok Kamphaeng Saen East: Landfill Gas to Electricity ProjectVerra VCS 783ThailandWithdrawnInactive2026-09-20*
Bangkok Kamphaeng Saen West: Landfill Gas to Electricity ProjectVerra VCS 785ThailandWithdrawnInactive2026-09-20*
Banpong Tapioca Flour Industrial Wastewater Treatment and Biogas Utilisation ProjectVerra VCS 405ThailandRegisteredRegistered2026-09-20*
Biomass powered process heat production and use project at KangwalVerra VCS 59ThailandLate to VerifyAt risk2026-09-20*
Cassava Waste To Energy Project, Kalasin, Thailand (CWTE project)Verra VCS 457ThailandLate to VerifyAt risk2026-09-20*
Chakangrao Starch wastewater treatment and biogas utilization projectVerra VCS 407ThailandLate to VerifyAt risk2026-09-20*
Chao Khun Agro Biogas Energy ProjectVerra VCS 41ThailandLate to VerifyAt risk2026-09-20*
Chol Charoen Group Wastewater Treatment with Biogas System I (Chacherngsao)Verra VCS 428ThailandRegisteredRegistered2026-09-20*
Chol Charoen Group Wastewater Treatment with Biogas System I (Cholburi)Verra VCS 430ThailandRegisteredRegistered2026-09-20*
Chol Charoen Group Wastewater Treatment with Biogas System I (Kampangpet)Verra VCS 467ThailandLate to VerifyAt risk2026-09-20*
Chol Charoen Group Wastewater Treatment with Biogas System I (Khonkaen)Verra VCS 427ThailandRegisteredRegistered2026-09-20*
Chorchaiwat Wastewater Treatment and Biogas Utilization ProjectVerra VCS 411ThailandRegisteredRegistered2026-09-20*
CYY Biopower Wastewater treatment plant including biogas reuse for thermal oil replacement and electricity generation Project, ThailandVerra VCS 2261ThailandRegisteredRegistered2026-09-20*
CYY Global Plus Wastewater Treatment and Biogas Utilization ProjectVerra VCS 2296ThailandRegisteredRegistered2026-09-20*
FST SMALL-SCALE SOLAR POWER PLANT IN KAMPHAENG PHET, THAILANDVerra VCS 4600ThailandRegisteredRegistered2026-09-20*
Installation of high efficiency wood burning cookstoves in ThailandVerra VCS 2522ThailandVerification approval requestedRegistered2026-09-20*
Installation of high efficiency wood burning cookstoves in Thailand – Project 2Verra VCS 4315ThailandWithdrawnInactive2026-09-20*
JAROENSOMPONG CORPORATION RACHATHEWA LANDFILL GAS TO ENERGYVerra VCS 585ThailandLate to VerifyAt risk2026-09-20*
Jiratpattana Biogas Energy ProjectVerra VCS 44ThailandLate to VerifyAt risk2026-09-20*
K.R. ONE IN THAILANDVerra VCS 2001ThailandRegisteredRegistered2026-09-20*
K.R.S. THREE IN THAILANDVerra VCS 2000ThailandRegisteredRegistered2026-09-20*
Kaona Power Supply Biomass Cogeneration ProjectVerra VCS 366ThailandLate to VerifyAt risk2026-09-20*
Kitroongruang Biogas Energy ProjectVerra VCS 367ThailandLate to VerifyAt risk2026-09-20*
KRISSANA WIND POWER IN THAILANDVerra VCS 1999ThailandVerification approval requestedRegistered2026-09-20*
Maesod Wastewater Treatment and Biogas Utilisation ProjectVerra VCS 2527ThailandRegisteredRegistered2026-09-20*
Methane emissions reduction through feed supplement for ruminant animals in Thailand by AgCoTechVerra VCS 5735ThailandPipeline Listing (under development) approvedPipeline2026-09-20*
Mungcharoen Green Power - 9.9 MW Rice Husk Fired Power Plant ProjectVerra VCS 256ThailandLate to VerifyAt risk2026-09-20*
Northern Fuel Pipeline Transportation Project, ThailandVerra VCS 1852ThailandRegisteredRegistered2026-09-20*
P.S.C Starch Wastewater Treatment and Biogas Utilization ProjectVerra VCS 417ThailandLate to VerifyAt risk2026-09-20*
Ratchaburi Farms Biogas Project at Nong Bua FarmVerra VCS 42ThailandLate to VerifyAt risk2026-09-20*
Ratchaburi Farms Biogas Project at SPM FarmVerra VCS 67ThailandLate to VerifyAt risk2026-09-20*
Ratchaburi Farms Biogas Project at Veerachai FarmVerra VCS 461ThailandLate to VerifyAt risk2026-09-20*
Reduction of GHG emissions in Propylene Oxide production at MTP HPPO Manufacturing Co., LtdVerra VCS 1502ThailandLate to VerifyAt risk2026-09-20*
Sahamitr Tapioca Chonburi Wastewater Treatment and Biogas Utilization ProjectVerra VCS 425ThailandLate to VerifyAt risk2026-09-20*
Saraff Energy EFB to electricity projectVerra VCS 1157ThailandLate to VerifyAt risk2026-09-20*
SD Biosupply Wastewater Treatment and Biogas Utilization ProjectVerra VCS 416ThailandRegisteredRegistered2026-09-20*
Siam Cement Biomass ProjectVerra VCS 403ThailandLate to VerifyAt risk2026-09-20*
Siam Quality Starch Wastewater Treatment and Energy Generation Project in Chaiyaphum, ThailandVerra VCS 913ThailandLate to VerifyAt risk2026-09-20*
SLEEK EV Project in ThailandVerra VCS 5995ThailandUnder validation (Public comment period closed)In validation2026-09-20*
SOLAR PV BESS AND CBG HYBRID PROJECT IN THAILANDVerra VCS 4846ThailandRegisteredRegistered2026-09-20*
SOLAR ROOFTOP PROJECT NAKHON PATHOM, THAILANDVerra VCS 4844ThailandUnder validation (Public comment period closed)In validation2026-09-20*
Starch Plus Wastewater Treatment And Biogas Utilisation ProjectVerra VCS 4848ThailandRegisteredRegistered2026-09-20*
Switching from Internal Combustion Engine Vehicles to Electric Vehicles of RÊVER Automotive’s Customers, ThailandVerra VCS 4733ThailandRegisteredRegistered2026-09-20*
THAILAND CARBON PROGRAM OF IMPROVED AGRICULTURAL LAND MANAGEMENT IN THE AREAS OF THE NORTHEAST PROJECTVerra VCS 5932ThailandUnder validation (Public comment period closed)In validation2026-09-20*
THAILAND CARBON PROGRAM OF RICE-FIELD FOR ALTERNATIVE WET AND DRY IN THE AREAS OF THE CENTRAL AND NORTHERNVerra VCS 5814ThailandUnder validation (Public comment period closed)In validation2026-09-20*
THAMMA RAKSA - REFORESTATION AND LAND RESTORATION IN THAILANDVerra VCS 3581ThailandPipeline Listing (under development) approvedPipeline2026-09-20*
Thanawat wastewater treatment and biogas utilization projectVerra VCS 408ThailandLate to VerifyAt risk2026-09-20*
The SPM Group Biogas ProjectVerra VCS 446ThailandLate to VerifyAt risk2026-09-20*
The VCF Group Biogas Projects at Nipat and Songphol FarmVerra VCS 452ThailandLate to VerifyAt risk2026-09-20*
THEPARAK WIND IN THAILANDVerra VCS 2002ThailandRegisteredRegistered2026-09-20*
TROPICAL WIND IN THAILANDVerra VCS 1997ThailandRegisteredRegistered2026-09-20*
VP Biosupply Wastewater Treatment and Biogas Utilization ProjectVerra VCS 415ThailandRegisteredRegistered2026-09-20*
Wastewater Treatment with Biogas Production (UASB) and Heat Utilization at General Starch Co Ltd.Verra VCS 82ThailandLate to VerifyAt risk2026-09-20*
Wastewater Treatment with Biogas System in Palm Oil Mill at Sawi, Chumporn,ThailandVerra VCS 426ThailandLate to VerifyAt risk2026-09-20*
Wastewater Treatment with Biogas Technology in a Tapioca Processing Plant at P.V.D. International Company Limited, ThailandVerra VCS 449ThailandLate to VerifyAt risk2026-09-20*
Wastewater Treatment with Biogas Technology in Tapioca Processing Plant at Roi Et Flour Company Limited, ThailandVerra VCS 401ThailandLate to VerifyAt risk2026-09-20*
West Huaybong 2 wind farm projectVerra VCS 2062ThailandWithdrawnInactive2026-09-20*
West Huaybong 3 wind farm projectVerra VCS 2006ThailandRejected by AdministratorInactive2026-09-20*

* already listed when we started reading that registry daily; the listing date is earlier.