Countries › Türkiye › Gold Standard 175
Karadere Wind Power Plant
- Registry
- Gold Standard · ID 175 · registry page
- Location
- Türkiye
- Registry status
- GOLD_STANDARD_CERTIFIED_PROJECT
- Status (Carbon.Supply classification)
- Registered
- Type (Carbon.Supply classification)
- Renewable Energy / Wind / Reduction (from the Berkeley Carbon Trading Project database)
- Proponent (registry's words)
- Fiba Yenilenebilir Enerji Holding A.Ş
- Developer page (Carbon.Supply classification)
- Fiba Yenilenebilir Enerji Holding A.Ş
- Project type
- Wind
- Estimated annual reductions
- 62,700 tCO2e per year (registry estimate)
- Credits issued
- 345,356 (Berkeley Carbon Trading Project 2026-08)
- Credits retired
- 306,101 (Berkeley Carbon Trading Project 2026-08)
- Labels
- EMISSION_REDUCTION
- SDGs
- Goal 13: Climate Action, Goal 7: Affordable and Clean Energy, Goal 8: Decent Work and Economic Growth
- Programme structure
- Standalone
- Documents
- project documents
Key dates
- Crediting period
- 2014-06-21 to 2028-06-20
- First seen by us
- 2026-09-20 (already listed then)
Status timeline
- 2026-09-20 Already listed on Gold Standard when we started reading it daily
- status: GOLD_STANDARD_CERTIFIED_PROJECT
- 2026-10-05 → 2026-10-06 Details changed
- methodology: AMS-I.D. Grid connected renewable electricity generation → blank
- estimated annual reductions: 32000 → 62700
Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.