Countries › Türkiye › Verra VCS 1014
Yamanli III Hydoeletric Power Plant
- Registry
- Verra VCS · ID 1014 · registry page
- Location
- district of Saimbeyli, Mediterranean Region, in the province of Adana, Türkiye
- Registry status
- Registered
- Status (Carbon.Supply classification)
- Registered
- Type (Carbon.Supply classification)
- Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
- Proponent (registry's words)
- Akenerji Elektrik Uretim A.S. (PP)
- Developer page (Carbon.Supply classification)
- Akenerji Elektrik Uretim A.S
- Methodology
- ACM0002 (Version 22)
- Sectoral scope
- Energy industries (renewable/non-renewable sources)
- Validation / verification body
- TUV Rheinland (China) Ltd.
- Estimated annual reductions
- 112,277 tCO2e per year (registry estimate)
- Issued units
- None shown
- Credits issued
- 0 (Berkeley Carbon Trading Project 2026-08)
- Credits retired
- 0 (Berkeley Carbon Trading Project 2026-08)
Key dates
- Project start
- 2012-05-12
- Registered / validated
- 2020-04-06
- Crediting period 2
- 2022-08-01 to 2032-07-31
- First seen by us
- 2026-09-20 (already listed then)
Status timeline
- 2026-09-20 Already listed on Verra VCS when we started reading it daily
- status: Registered
Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.