Countries › Türkiye › Verra VCS 1297
Eren 37 MW Hydroelectric Power Plant
- Registry
- Verra VCS · ID 1297 · registry page
- Location
- Safranbolu District, Karabuk Province, Türkiye
- Registry status
- Crediting Period Renewal Requested
- Status (Carbon.Supply classification)
- Registered
- Type (Carbon.Supply classification)
- Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
- Proponent (registry's words)
- IRMAK Enerji. Üretim San. ve Tic. Ltd. Sti.
- Developer page (Carbon.Supply classification)
- IRMAK Enerji. Üretim San. ve Tic. Ltd. Sti.
- Methodology
- ACM0002 (Version 22)
- Sectoral scope
- Energy industries (renewable/non-renewable sources)
- Validation / verification body
- TUV Rheinland Energie und Umwelt GmbH
- Estimated annual reductions
- 73,787 tCO2e per year (registry estimate)
- Issued units
- Yes
- Credits issued
- 272,541 (registry)
- Credits retired
- 630 (registry)
Key dates
- Project start
- 2014-12-04
- Registered / validated
- 2020-04-06
- Crediting period 1
- 2014-12-04 to 2024-12-03
- Pending request submitted
- 2026-10-14
- First seen by us
- 2026-09-20 (already listed then)
- Current status since
- 2026-10-15
Status timeline
- 2026-09-20 Already listed on Verra VCS when we started reading it daily
- status: Registered
- 2026-10-14 → 2026-10-15 Status changed
- Registered → Crediting Period Renewal Requested
- 2026-11-06 → 2026-11-07 Details changed
- methodology: ACM0002 (Version 14) → ACM0002 (Version 22)
Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.