LatestCountriesDevelopersSearch

Countries › China › Verra VCS 1433

LinCang Yun County, XinTangFang Hydropower Station Project

Registry
Verra VCS · ID 1433 · registry page
Location
LinCang City, Yunnan Province, China
Registry status
Late to Verify
Status (Carbon.Supply classification)
At risk
Type (Carbon.Supply classification)
Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
LinCang Yun Tou Yue Dian Hydropower Development Co.,Ltd
Developer page (Carbon.Supply classification)
LinCang Yun Tou Yue Dian Hydropower Development Co.,Ltd
Methodology
ACM0002 (Version NA)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
RINA Services S.p.A
Estimated annual reductions
35,166 tCO2e per year (registry estimate)
Issued units
None shown
Credits issued
0 (Berkeley Carbon Trading Project 2026-08)
Credits retired
0 (Berkeley Carbon Trading Project 2026-08)

Key dates

Project start
2009-08-31
Registered / validated
2014-12-20
Crediting period 1
2009-08-31 to 2016-08-30
First seen by us
2026-09-20 (already listed then)

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Late to Verify

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.