Kirazlık Hydroelectric Power Plant Project

Registry
Verra VCS · ID 2092 · registry page
Location
Botan River, Eastern Anatolia Region, Siirt Province, Türkiye
Registry status
Registered
Status (Carbon.Supply classification)
Registered
Type (Carbon.Supply classification)
Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
Baren Enerji Sanayi ve Ticaret Üretim A.Ş.
Developer page (Carbon.Supply classification)
Baren Enerji Sanayi ve Ticaret Üretim A.Ş.
Methodology
ACM0002 (Version 13)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
TUV Rheinland Energie und Umwelt GmbH
Estimated annual reductions
81,307 tCO2e per year (registry estimate)
Issued units
Yes
Credits issued
479,318 (Berkeley Carbon Trading Project 2026-08)
Credits retired
116,006 (Berkeley Carbon Trading Project 2026-08)

Key dates

Project start
2013-12-05
Registered / validated
2021-03-18
Crediting period 1
2013-12-05 to 2023-12-04
First seen by us
2026-09-20 (already listed then)

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Registered

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.