Kargilik 24 MW Hydropower Plant, Turkey

Registry
Verra VCS · ID 264 · registry page
Location
Andirin town, Kahramanmaras Province, Türkiye
Registry status
Late to Verify
Status (Carbon.Supply classification)
At risk
Type (Carbon.Supply classification)
Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
Tektuð Elektrik Üretim A.Þ.
Developer page (Carbon.Supply classification)
Tektuð Elektrik Üretim A.Þ.
Methodology
ACM0002 (Version 9)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
Bureau Veritas India Private Limited
Estimated annual reductions
40,528 tCO2e per year (registry estimate)
Issued units
Yes
Credits issued
415,172 (Berkeley Carbon Trading Project 2026-08)
Credits retired
262,893 (Berkeley Carbon Trading Project 2026-08)

Key dates

Project start
2005-04-24
Registered / validated
2020-04-06
Crediting period 2
2016-03-28 to 2026-03-27
First seen by us
2026-09-20 (already listed then)

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Late to Verify

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.