Feke I 29.4 MW Hydroelectric Power Plant

Registry
Verra VCS · ID 533 · registry page
Location
Adana Province, Adana Province, Türkiye
Registry status
Withdrawn
Status (Carbon.Supply classification)
Inactive
Type (Carbon.Supply classification)
Renewable Energy / Hydropower / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
Akenerji Elektrik Uretim A.S
Developer page (Carbon.Supply classification)
Akenerji Elektrik Uretim A.S
Methodology
ACM0002 (Version NA)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
Bureau Veritas India Private Limited
Estimated annual reductions
63,999 tCO2e per year (registry estimate)
Issued units
None shown
Credits issued
0 (Berkeley Carbon Trading Project 2026-08)
Credits retired
0 (Berkeley Carbon Trading Project 2026-08)

Key dates

Project start
2011-03-01
Registered / validated
2020-04-06
First seen by us
2026-09-20 (already listed then)

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Withdrawn

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.