Countries › South Africa › Verra VCS 5146

Redstone CSP project

Registry
Verra VCS · ID 5146 · registry page
Location
Postmasburg, Northern Cape, South Africa
Registry status
Verification approval requested
Status (Carbon.Supply classification)
Registered
Type (Carbon.Supply classification)
Renewable Energy / Solar - Centralized / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
ACWA Power Solar Reserve Redstone Solar Thermal Power Plant (RF) (Pty) Ltd (PP),Anthesis B.V. (PP)
Developer pages (Carbon.Supply classification)
ACWA Power Solar Reserve Redstone Solar Thermal Power Plant (RF) (Pty) Ltd · Anthesis B.V.
Methodology
ACM0002 (Version 22)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
Carbon Check (India) Private Ltd.
Estimated annual reductions
478,316 tCO2e per year (registry estimate)
Area
700 ha (as the proponent entered it)
Issued units
None shown
Credits issued
0 (registry)
Credits retired
0 (registry)
Website
https://acwapower.com/en/projects/redstone-csp-ipp/

Key dates

Project start
2024-11-30
Registered / validated
2026-01-26
Crediting period 1
2024-11-30 to 2031-11-29
Pending request submitted
2026-10-09
First seen by us
2026-09-20 (already listed then)
Current status since
2026-10-10

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Registered
  2. 2026-10-09 → 2026-10-10 Status changed
    • Registered → Verification approval requested
  3. 2026-10-29 → 2026-10-30 Details changed
    • proponent: Multiple Project Proponents → ACWA Power Solar Reserve Redstone Solar Thermal Power Plant (RF) (Pty) Ltd (PP),Anthesis B.V. (PP)

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.