LatestCountriesDevelopersSearch

Countries › India › Verra VCS 735

Wind power project by PMPL in Maharashtra

Registry
Verra VCS · ID 735 · registry page
Location
Dhule district, Maharashtra, India
Registry status
Late to Verify
Status (Carbon.Supply classification)
At risk
Type (Carbon.Supply classification)
Renewable Energy / Wind / Reduction (from the Berkeley Carbon Trading Project database)
Proponent (registry's words)
Patnaik Minerals Private Limited (PMPL)
Developer page (Carbon.Supply classification)
Patnaik Minerals Private Limited (PMPL)
Methodology
AMS-I.D. (Version NA)
Sectoral scope
Energy industries (renewable/non-renewable sources)
Validation / verification body
TÜV NORD CERT GmbH
Estimated annual reductions
22,614 tCO2e per year (registry estimate)
Issued units
Yes
Credits issued
70,980 (Berkeley Carbon Trading Project 2026-08)
Credits retired
56,623 (Berkeley Carbon Trading Project 2026-08)

Key dates

Project start
2006-09-26
Registered / validated
2020-04-06
Crediting period 1
2006-09-26 to 2016-09-25
First seen by us
2026-09-20 (already listed then)

Status timeline

  1. 2026-09-20 Already listed on Verra VCS when we started reading it daily
    • status: Late to Verify

Dates are the daily reads between which we saw the change; the registry may have made it earlier that day or in that window.